Latrobe Magnesium is on the home stretch with construction of its Latrobe Valley Demonstration Plant in Victoria at 70% completion with first magnesium metal production on track to start in H2 2026.
This marks significant progress for Phase 1B, which stood at around 50% completion just five weeks ago.